Direct answer: track the choice, consequence and last responsible date
Before procurement, an office fit-out decision register should state exactly what must be decided, why it matters, the available options, evidence required, one accountable owner, contributors, approval route, target and last responsible dates, current status, linked drawings or specifications, affected packages, and any cost or programme consequence. It is not a meeting-minute archive. Its job is to make unresolved choices visible before they become substitutions, delays or uncoordinated orders. RIBA's Plan of Work organises projects around stage outcomes, tasks and information exchanges, and its toolbox includes a Design Responsibility Matrix. The same discipline is valuable in an office design-and-build project: decisions should have clear responsibility and arrive when the team can still act on them.
Choose decisions worth controlling
Begin with items that change what is bought, built or approved. Typical groups include workplace planning, landlord interfaces, partitions and doors, ceilings, lighting, mechanical and electrical services, IT and audiovisual responsibilities, furniture, finishes, signage, security, accessibility, sustainability objectives, testing and handover. A question such as whether a meeting room uses framed or frameless glazing is not just aesthetic: it may affect acoustic expectations, door hardware, ceiling interfaces, lead time and cost. Write each item as a question that can be closed, not a vague topic such as meeting rooms. Combine duplicates and link dependent decisions so the team can see which one must close first.
- Write a decision, not a discussion theme
- Name the affected room or package
- Record dependencies and downstream users
- Separate approval from technical review
Use two dates, not one
A target date supports normal workflow; a last responsible date marks the point after which delay changes cost, programme, coordination or quality. The second date should be agreed with the people procuring and delivering the work, not guessed from the meeting calendar. A carpet colour can remain open until the order deadline only if samples, quantities, substrate and performance are already settled. A partition type may need closure much earlier because it affects layouts, doors, services and authority or landlord submissions. Showing both dates helps the client distinguish a comfortable approval window from the real consequence of waiting.
Attach evidence and define approval
Every material decision should point to the evidence needed for a responsible choice: coordinated drawing, sample, mock-up, technical submission, cost comparison, lead-time confirmation, specialist review or landlord comment. The register should identify who recommends, who reviews and who approves. One person can hold more than one role, but the distinction still matters. Avoid closing an item with informal phrases such as looks fine when the decision affects measurable performance. State the accepted option and revision. If approval is conditional, record the condition and keep the item open until it is satisfied. RIBA's Job Book resources reinforce the value of systematic checklists and records aligned with project stages.
- Link the exact drawing or sample revision
- Record the approved option in words
- Capture conditions and residual actions
- Retain a short reason where trade-offs matter
Connect decisions to procurement and change control
A closed register item should update the controlled drawings, specification, schedule and procurement package that rely on it. A changed decision should not quietly overwrite history. Record the previous position, reason, authorisation, affected information and assessed consequence. This is especially important when furniture, IT, audiovisual, security and specialist equipment sit outside the main contractor's supply. The register can expose gaps: the floor box may be ordered by one party while the furniture power module belongs to another. Linking the choice to a responsibility schedule reduces interface assumptions before orders are placed.
Planning example
A 60-person office includes three glazed meeting rooms. The concept specifies high speech privacy, but the client has not approved the partition and door package. The register splits the issue into one controlled decision: approve the tested partition-door-ceiling solution against the agreed privacy brief. Evidence includes the specialist proposal, coordinated head and jamb details, door hardware, service-penetration strategy, cost and lead time. The client is accountable; the designer, acoustic specialist and contractor contribute. The target date precedes detailed coordination, while the last responsible date precedes order release. Approval updates the partition schedule and procurement package. A later request for a different door is treated as a change because it could affect the complete assembly.
- Decision owner: named client representative
- Evidence: performance proposal and coordinated details
- Affected packages: partitions, doors, ceilings and services
- Closure: approved assembly and document revisions recorded
A concise pre-procurement checklist
Review the register by package and by room. Confirm that each item has one accountable owner, contributors, evidence, target date, last responsible date and status. Check that closed decisions appear in current design information; pending decisions are visible in the programme and cost plan; landlord and specialist comments are assigned; long-lead orders have no hidden assumptions; operator-supplied items have interfaces; and superseded approvals remain traceable. Keep the status language simple: open, information required, under review, approved with action, closed or changed. Do not use the register to replace contracts, professional duties, technical design or statutory approvals.
- No anonymous owner
- No decision without affected documents
- No closed item based on superseded evidence
- No order released against an unresolved critical interface
- No change without consequence review
Limitations and next step
The ideal register format depends on procurement route, contract, team structure and project complexity. It cannot manufacture certainty where the brief or responsibility boundaries remain unresolved. Before the next procurement release, hold a 45-minute decision review with the client lead, design lead, delivery lead and package owners. Focus only on decisions that are late, high-consequence or blocking other work. Agree the owner, evidence and last responsible date for each, then issue the updated register with the meeting actions. A small, actively governed register is more useful than a large spreadsheet that records discussion but never closes choices.