The direct answer

The brief should define who may enter each zone, when and by which credential; how visitors are invited, verified, hosted and released; what happens during an emergency or system outage; what personal data is collected; and which doors, lifts or reception points the system touches. It should then assign design, certification, installation, IT, facilities and operating responsibilities. Door hardware cannot be coordinated from a reader symbol alone. The approved security strategy, life-safety design, accessibility needs and visitor experience must meet at the same threshold.

Begin with access zones, not devices

Divide the workplace by operational need: public reception, hosted visitor areas, general staff space, out-of-hours zones and genuinely restricted rooms. For each boundary, state the user groups, hours, escort rule and exceptional cases such as cleaners, maintenance staff or deliveries. Avoid assuming that more controlled doors mean better security. Each boundary needs an owner who can approve and revoke access. This zoning exercise also reveals where a welcoming open route can remain separate from a controlled staff route, preventing the reception desk from becoming an obstacle course.

Check the Dubai review route early

Dubai's Security Industry Regulatory Agency publishes a Preventive Systems Manual that includes access-control specifications, and its current security-system certification service refers applicants to requirements based on building or activity type. That does not mean every office follows the same approval route. The client and appointed security consultant should confirm whether the property, tenancy and activity trigger a specific SIRA, landlord or other review, and should identify licensed parties where required. Record the answer before the door schedule and security package are issued rather than adding a certification task near handover.

Coordinate each controlled opening

For every controlled door, the schedule should bring together the leaf and frame, lock or strike, closer, exit hardware, reader, door contact, request-to-exit device, power supply, cable transfer and interfaces with the fire and building-management systems. It must also preserve safe egress and the project's accessibility strategy. This is specialist work: the architect, fire and life-safety consultant, security designer, electrical engineer and door supplier should review the same door-by-door information. A late access-control change can invalidate frame preparation, finish warranties or testing, so procurement should follow approved coordinated details.

Design the visitor sequence

Map the journey from invitation to departure. Decide whether guests arrive with a host, QR code, temporary card or receptionist-issued pass; where they wait; what identity information is actually needed; which areas require escort; and how credentials are returned or expire. Keep the reception team's sightline and workload realistic. Delivery riders, interview candidates, vendors and event guests may need different flows. The design should avoid exposing staff-only screens or allowing a queue to block the accessible route. A secure threshold can still feel calm when the process, furniture and door positions are planned together.

Set privacy and operating rules before configuration

Visitor and credential systems may process personal data. The UAE Government describes Federal Decree-Law No. 45 of 2021 as a framework for confidentiality, privacy and governance of personal-data collection, processing and storage. Obtain appropriate legal and privacy advice for the organisation and any applicable free-zone regime. The brief should ask for the minimum data set, purpose, access permissions, retention period, deletion process, audit ownership and vendor responsibilities. A receptionist should not have to invent these rules after the platform is installed.

  • Purpose and minimum visitor information
  • Who can view, correct or export records
  • How long records and credentials remain active
  • Host and reception responsibilities
  • Process for lost cards, revocation and exceptions
  • Vendor support and incident escalation

Planning example

A fictional 70-person office receives clients, couriers and service technicians. The first plan puts one controlled glass door directly behind reception and gives all visitors the same temporary pass. The review separates a public meeting suite from the staff workplace, creates a delivery handover point before the controlled line, and defines a hosted route for technicians. The security consultant coordinates reader and lock interfaces with the door supplier, while the client defines credential expiry and visitor-record retention with its advisers. This is a planning example, not a SIRA approval determination or a security design for a real facility.

Pre-order checklist

Review this list before doors, frames, hardware or control equipment are ordered.

  • Public, hosted, staff, after-hours and restricted zones are agreed
  • User groups, hours, escort rules and zone owners are documented
  • Applicable SIRA, landlord and project review routes are confirmed
  • Each controlled opening has a coordinated door and interface schedule
  • Emergency release, safe egress and outage behaviour are specialist-reviewed
  • Accessible approach, reader reach and clear route are coordinated
  • Visitor invitation, verification, badging and departure flows are tested
  • Personal-data purpose, access and retention rules are approved
  • Testing, training, handover and ongoing administration have named owners

Limitations and next step

This framework does not replace a threat assessment, SIRA advice, fire and life-safety design, accessibility review, electrical engineering, data-protection advice or manufacturer details. Security information should be shared only with authorised project parties, and public drawings should not expose sensitive operating logic. Hold a controlled access workshop with the client, workplace designer, appointed security consultant, IT, facilities and reception representatives. Issue the resulting zone plan, visitor journey, door interface matrix and responsibility schedule before procurement. That creates a reviewable brief without turning the journal into instructions for defeating or installing a security system.

Sources & further reading

Make this useful for your project.

A review of your property and priorities can turn general guidance into a defined brief.

Explore Workplace planningDiscuss your project
Return to the journal